Al Rowad Private SchoolsKhobar
RS4IT
A platform and app for Al Rowad parents: attendance, grades, messages with teachers and school fees.
Current phase
Progress
71%
5 of 7 phases
Delivery
3 Dec
12 days left
Started 6 Jul
People
Acceptance testing with the school
Feedback goes into the conversation as change requests.
| # | Phase | Owner | Due | Status | Actions |
|---|---|---|---|---|---|
Requirements 6 Jul → 20 Jul | Khalid Al-Shammari Senior Web Developer | 20 Jul Finished 20 Jul | Change status | ||
Interface design 21 Jul → 13 Aug | Khalid Al-Shammari Senior Web Developer | 13 Aug Finished 12 Aug | Change status | ||
Build the platform 16 Aug → 22 Oct | Khalid Al-Shammari Senior Web Developer | 22 Oct Finished 20 Oct | Change status | ||
Mobile app 13 Sept → 5 Nov | Yousef Al-Qahtani Mobile Developer | 5 Nov Finished 5 Nov | Change status | ||
School uploads student data 25 Oct → 8 Nov | Saad Al-Hamdan Client side | 8 Nov Finished 8 Nov | Change status | ||
| 6 | Acceptance testing with the school Feedback goes into the conversation as change requests. 12 Nov → 27 Nov | Maha Al-Jabr Client side | 27 Nov In 6 days | Change status | |
| 7 | Launch and staff training 29 Nov → 3 Dec | Khalid Al-Shammari Senior Web Developer | 3 Dec In 12 days | Change status |
Requirements
6 Jul → 20 Jul
Khalid Al-Shammari
Senior Web Developer
20 Jul
Finished 20 Jul
Interface design
21 Jul → 13 Aug
Khalid Al-Shammari
Senior Web Developer
13 Aug
Finished 12 Aug
Build the platform
16 Aug → 22 Oct
Khalid Al-Shammari
Senior Web Developer
22 Oct
Finished 20 Oct
Mobile app
13 Sept → 5 Nov
Yousef Al-Qahtani
Mobile Developer
5 Nov
Finished 5 Nov
School uploads student data
25 Oct → 8 Nov
Saad Al-Hamdan
Client side8 Nov
Finished 8 Nov
Acceptance testing with the school
Feedback goes into the conversation as change requests.
12 Nov → 27 Nov
Maha Al-Jabr
Client side27 Nov
In 6 days
Launch and staff training
29 Nov → 3 Dec
Khalid Al-Shammari
Senior Web Developer
3 Dec
In 12 days
Every change is written to the conversation under the name of who made it
Saad Al-Hamdan finished «School uploads student data»
Yousef Al-Qahtani finished «Mobile app»via MCP
Khalid Al-Shammari finished «Build the platform»
Khalid Al-Shammari finished «Requirements»