Ber Eastern Province CharityDammam
RS4IT
A donations platform for Ber Charity: campaigns, monthly sponsorships, mada and Apple Pay, automatic receipts.
Current phase
Progress
50%
3 of 6 phases
Delivery
30 Nov
9 days left
Started 17 Aug
People
| # | Phase | Owner | Due | Status | Actions |
|---|---|---|---|---|---|
Requirements 17 Aug → 27 Aug | Faisal Al-Otaibi Managing Director | 27 Aug Finished 27 Aug | Change status | ||
Platform design 30 Aug → 28 Sept | Khalid Al-Shammari Senior Web Developer | 28 Sept Finished 28 Sept | Change status | ||
Client approves page copy 29 Sept → 15 Oct | Mansour Al-Khalidi Client side | 15 Oct Finished 4 Nov | Change status | ||
| 4 | Build the platform and campaigns Delayed by the copy approval; campaign pages ship first. 1 Oct → 12 Nov | Khalid Al-Shammari Senior Web Developer | 12 Nov 9 days late | Change status | |
| 5 | Payment gateway (mada, Apple Pay) Gateway contract arrived 16 November; testing in the sandbox. 8 Nov → 18 Nov | Reem Al-Dosari Backend & Integrations Developer | 18 Nov 3 days late | Change status | |
| 6 | Testing and launch 22 Nov → 30 Nov | Khalid Al-Shammari Senior Web Developer | 30 Nov In 9 days | Change status |
Requirements
17 Aug → 27 Aug
Faisal Al-Otaibi
Managing Director
27 Aug
Finished 27 Aug
Platform design
30 Aug → 28 Sept
Khalid Al-Shammari
Senior Web Developer
28 Sept
Finished 28 Sept
Client approves page copy
29 Sept → 15 Oct
Mansour Al-Khalidi
Client side15 Oct
Finished 4 Nov
Build the platform and campaigns
Delayed by the copy approval; campaign pages ship first.
1 Oct → 12 Nov
Khalid Al-Shammari
Senior Web Developer
12 Nov
9 days late
Payment gateway (mada, Apple Pay)
Gateway contract arrived 16 November; testing in the sandbox.
8 Nov → 18 Nov
Reem Al-Dosari
Backend & Integrations Developer
18 Nov
3 days late
Testing and launch
22 Nov → 30 Nov
Khalid Al-Shammari
Senior Web Developer
30 Nov
In 9 days
Every change is written to the conversation under the name of who made it
«Payment gateway (mada, Apple Pay)» is past its due date
«Build the platform and campaigns» is past its due date
Mansour Al-Khalidi finished «Client approves page copy»
«Client approves page copy» is past its due date
Khalid Al-Shammari finished «Platform design»
Faisal Al-Otaibi finished «Requirements»