Ber Eastern Province CharityDammam
RS4IT
A donations platform for Ber Charity: campaigns, monthly sponsorships, mada and Apple Pay, automatic receipts.
Current phase
Progress
50%
3 of 6 phases
Delivery
30 Nov
9 days left
Started 17 Aug
People
Khalid Al-Shammari finished «Platform design»
We want donors to give in the name of a parent or friend, with a gift card sent to that person by SMS.
Faisal Al-Otaibi marked «Gift a donation in someone else’s name» as «Accepted»
Faisal Al-Otaibi moved the delivery date from 5 Nov to 12 Nov
«Client approves page copy» is past its due date
Mr. Mansour, we have been waiting for the page copy since 15 October. We are continuing with placeholder text for now, but every week of delay pushes the launch back.
Apologies for the delay. The copy is with the board for review and I will send it as soon as it is approved.
Mansour Al-Khalidi finished «Client approves page copy»
«Build the platform and campaigns» is past its due date
«Payment gateway (mada, Apple Pay)» is past its due date
To be frank: with the copy arriving 20 days late and the contract on 16 November, 30 November is no longer realistic. We suggest launching on 10 December with a full week of testing, and await your approval.
Understood, and the delay was on our side. What matters is that the platform is ready before the winter campaign in mid-December.
mada payments work on the test environment. Apple Pay needs the site domain verified from the charity’s gateway account; I have emailed the steps to Mr. Mansour.